### The Scrum Master observes the Product Owner struggling with ordering the Product Backlog. What is an appropriate action for the Scrum Master to take? (choose the best answer)
673
673
674
674
-[ ] Suggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog.
675
-
-[x] Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.
676
-
-[] Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
675
+
-[] Suggest that the Development Team does the ordering to be sure that it is a feasible ordering of work.
676
+
-[x] Offer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
677
677
-[ ] Present the Product Owner with an ordered Product Backlog to use.
678
678
-[ ] Encourage the Product Owner to work with the Development Team to see which items technically are fastest to implement.